Home » Buy and hold real estate investing properties » 4th House: Raised Bungalow Build » House Construction Schedule for Owner Builders

4th House: Raised Bungalow Build Buy and hold real estate investing properties Real Estate Investing Tips

House Construction Schedule for Owner Builders

Are you planning on building your own house? Having a house construction schedule can help you understand the different stages of building and keep everything organized.

Building our own home had always been a dream of ours. In 2016, we bought 30 acres of land in a rural community south of Ottawa, Ontario, and built a raised bungalow in 2019. We decided to act as our own general contractors, both to save money and to challenge ourselves.

Even though we’d completed plenty of home renovations before, building an entire house was a completely different experience. There were so many decisions to make, subcontractors to coordinate, and things to keep track of. I quickly realized that having a construction schedule was one of the best ways to stay organized throughout the process.

You can read about our house-building experience in my weekly home construction updates.

What is an owner builder?

An owner-builder is someone who takes on the role of general contractor when building their own home. Instead of hiring a general contractor to manage the entire project, you coordinate the construction process yourself. This includes getting quotes, hiring subcontractors, ordering materials, managing the budget, making decisions, and keeping everything moving according to the construction schedule. One of the main reasons we decided to be our own general contractors was to save money. While there can be significant savings, it also takes a lot of time, organization, and research.

When we started planning our house, I knew very little about the construction process. We’d done plenty of renovations, but building an entire house was completely different. What I really needed was a simple schedule that showed me what needed to happen, when it needed to happen, and approximately how long each stage would take. I’m a list person. I like writing things down and crossing them off when they’re done. Having a construction schedule helped me feel organized, even when the building process felt a little chaotic.

Custom House Construction Schedule

So I created a simple construction schedule with the general phases of building.

 

When we were building our house, I wanted a simple way to organize the different stages of construction and keep track of our budget. So I created two Excel worksheets to help us plan the project.

The Home Construction Schedule and Budget Worksheet includes:

  • Custom House Construction Schedule: Enter your project information to calculate estimated start dates and timelines for the different stages of construction.
  • Home Construction Budget Worksheet: Enter your total budget and lot purchase price to generate estimated costs for the major parts of your house build.

Both worksheets are included in one downloadable Excel file, with instructions to help you enter your information. Of course, every house build is different. Construction timelines and costs depend on the size and complexity of the house, subcontractor availability, material deliveries, and how much work you plan to do yourself. These worksheets are intended as planning tools to help you get organized.

Get the worksheet

You can also read more about organizing your finances when building your own house.

 


11 Comments

Previous Post: « 7 Easy Kid Bedroom Organization Ideas
Next Post: Upstairs Hallway And Interior Trim: One Room Challenge Week 1 »

Reader Interactions

Comments

  1. Cristina says

    April 4, 2017 at 2:26 am

    I never thought about doing a schedule for the house construction. But this is a great idea!

    Reply
  2. Habiba says

    April 4, 2017 at 3:01 pm

    I think it’s such a big project to build a house and I envy your organizational skills!! Well done!

    Reply
  3. julie nichols says

    April 4, 2017 at 5:36 pm

    This is a great idea!
    Julie @ Love My Simple Home

    Reply
  4. createpraylove says

    April 4, 2017 at 10:19 pm

    I think you are going to save SO many future home builders a lot of time with this worksheet! This is awesome! <3

    Reply
    • jessvanderveen@gmail.com says

      April 5, 2017 at 9:39 pm

      I hope so!

      Reply
  5. Linsey says

    March 18, 2019 at 4:35 pm

    I tried to put in my email to get the worksheet, but it doesn’t seem to be working. Can you send one to me?

    Reply
    • Jessica Vanderveen says

      March 19, 2019 at 11:16 am

      Yes thanks for letting me know! I will email it to you

      Reply
      • Leslie says

        May 20, 2019 at 4:31 pm

        Hi Jessica! I’m also having trouble submitting my email address.

        Reply
  6. Leslie says

    May 20, 2019 at 2:53 pm

    Hi! I tried putting my email address in a couplr times and it doesn’t seem to be working. How can I get a copy of your worksheet? I’m hoping it can help me figure out where to start 😶😄

    Reply
    • Jessica Vanderveen says

      May 22, 2019 at 2:00 pm

      Yes I have a few things that aren’t working quite right on my site! Thanks for letting me know. I just sent you an email with two worksheets

      Reply

Trackbacks

  1. How to Organize Your Finances When You Build A House: Plus a Free Budget Worksheet • The Vanderveen House says:
    August 17, 2017 at 8:46 pm

    […] aspects that you need to pay attention to – time and money. I few months ago I wrote about creating a house construction schedule for keeping you on track with your time. Today I’m going to tell you what I have learned about how […]

    Reply

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.

Primary Sidebar

Welcome! We are Tony and Jessica Vanderveen, and we live in eastern Ontario. As a family we love to do DIY projects and home renovations. Find out more...

Looking for something?

Categories

  • Buy and hold real estate investing properties
    • 4th House: Raised Bungalow Build
    • Cabin Vacation Rental
    • Rental House
    • Waterfront Cabin
  • DIY Projects
    • Craft Ideas
    • Furniture Makeovers
    • Gardening
    • Outdoor Ideas
    • Woodworking
  • Fix and Flip Houses
    • First House
    • Flip House
    • Second House
    • Third House
  • Real Estate Investing Tips

Explore the Archives

Footer

You might also like

How to build deck stairs from pressure treated lumber

How to make a faux marble top coffee table

How NOT to make a live edge river coffee table

Melt and pour soap making for beginners

DIY end of year teacher gift using resin and school supplies

Copyright © 2026 · Divine theme by Restored 316

Copyright © 2026 · Divine Theme on Genesis Framework · WordPress · Log in

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish.Accept Read More
Privacy & Cookies Policy

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT
custom home construction schedule