onyWith most of the interior work on our waterfront cabin complete, it was time to focus on finishing the exterior and doing the landscaping. Over the late fall, we built a covered deck, finished the siding, and added a few final touches to the outside of the cabin. Once spring arrived, we turned our attention to the property, which still looked very much like a construction site. In this post, I’ll walk you through how we finished the exterior of our tiny cabin and transformed the surrounding property.
Building the Covered Deck and Stairs
By mid-November 2023, Tony had built a six-foot-deep deck across the front of the cabin. He used rough-cut posts for the uprights and rough-cut lumber for the roof joists. We then installed strapping and finished the roof with the same tin roofing we used on the cabin.


Once the tin was installed on the porch roof, I was able to finish installing the cedar shakes in the gable at the front of the cabin. You can read more about the earlier exterior work in my post about finishing the cabin exterior. Before installing the shakes, I made sure the window was properly sealed using Blueskin window flashing tape.


We continued installing the exterior siding, but by this point, it was getting into December, and the snow was starting to fly.


By Christmas, we had built a wide set of stairs off the front of the deck that extended almost the entire length of the cabin. We thought it would be a good idea to have wide stairs that could double as extra seating. We also wanted to keep the front of the deck as open as possible so we could enjoy the waterfront views, whether we were sitting inside the cabin or out on the deck.

The last step was finishing the deck railings, which we managed to complete just before winter really set in.

Making a Custom Cabin Sign
If you remember our original cabin, we had a cute little wooden sign on the front with the cabin’s name, Lunenburg Lodge. We wanted to do something similar for the new cabin as a nod to the original, but with a new name. We had a piece of live-edge walnut, and a friend of ours was able to laser engrave the new name, Boyd Landing Lodge, into the wood. I finished the walnut with oil and installed the sign on the front of the cabin, along with some hooks.

Landscaping Around the Cabin
Once spring arrived and the ground was dry enough, we got back to work on the landscaping. The property still looked very much like a construction zone, so we brought in a load of dirt and used a mini excavator to spread it around the cabin. Once everything was levelled out, we planted grass seed.




Building a Covered Outdoor Dining Area
We also wanted to create a separate outdoor area for eating, closer to the waterfront. Tony and I built a simple 12-by-12-foot deck away from the cabin and used pressure-treated 4×4 posts for the uprights. We built simple roof trusses and covered the dining area with a heavy-duty marine tarp designed for outdoor use.


Cleaning up the waterfront
We also added a dock and did some cleanup along the shoreline. We wanted to make the waterfront a little more accessible while still keeping the area fairly natural.

And of course, while working at the cabin, we were once again reminded of the beautiful sunsets we get to enjoy over the water.

Finished cabin exterior
After months of construction, it was exciting to finally see the outside of the cabin and the surrounding property coming together. Between the covered deck, wide stairs, landscaping, and outdoor eating area, we had created a lot more usable outdoor space. With the exterior work complete, we were finally getting close to the end of our cabin rebuild. In my next post, I’ll share a complete tour of our finished waterfront cabin.